Wyoming-Jacksons Ferry 765-kV Project

 AEPs Power Line Project 600pxAmerican Electric Power


Project Description

Completed in 2006, American Electric Power’s 90-mile, 765kV Wyoming-Jacksons Ferry line runs from the Wyoming substation in West Virginia to the Jacksons Ferry substation in Virginia. After a lengthy permitting process lasting more than thirteen years and involving several state and federal agencies, the Wyoming-Jacksons Ferry line adopted many innovative environmental mitigation measures.

  • Visual mitigation
    • As much as possible, the line takes advantage of topography to limit visual impacts. This map (link) shows many bends in the Wyoming-Jacksons Ferry route, especially compared to nearby existing 345 kV transmission lines. The more circuitous route was selected to hide the line from view of roads, trails, and population centers.
    • The line was sited to cross the Appalachian Trail at the same site where the trail crosses Interstate Highway 77, specifically to limit visual impacts to hikers.
    • American Electric Power (AEP) used darker-than-customary steel on transmission towers to help towers blend in with the landscape along the trail. The company also used materials to cut down on reflective glare from conducting wires.
  • Sound levels
    • AEP cut down on audible buzzing from the Wyoming-Jacksons Ferry line by developing a unique six-bundle configuration for the extra-high voltage line, which reduced noise levels by half.
  • Selective clearing of right-of-way
    • Instead of completely clearing the rights-of-way, AEP leaves in place shorter trees, such as dogwoods and redbuds, to provide better habitat connectivity.
  • Helicopter construction
    • In order to minimize ground impacts during the construction phase, AEP used helicopters for hanging insulators, threading lead lines, transporting steel bundles and conductor reels, raising guyed-V towers in inaccessible sites, and transporting workers to worksites.

Resources


Organization: American Electric Power (AEP)
Location: West Virginia, Virginia
Project Phase: Construction (helicopters, visional/sound mitigation)